Symptom
While generating settlement rule for internal projects in "Generate Settlement Rules - Projects" app, below error occurs:
WBS Element XXXX.1.1
No strategy maintained for project profile P002
Environment
SAP S/4HANA Cloud Public Edition
Resolution
"Internal Projects" (P002) do not support settlement rule strategy.
In case you want to settle the costs, you need to manually maintain the settlement rules for the project and run the period end settlement at the end of the month.
Keywords
Settlement, WBS, Internal Project, Internal Projects, project, Strategy, Profile, P002, ORB500, No strategy maintained for project profile P002, S4_PC, PS-COS-PER-SE, CO-FIO , KBA , CO-OM-OPA-2CL , Overhead Orders (Public Cloud) , PPM-SCL-STR , Project Structure (Public Cloud) , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , How To