Symptom

The Inspected Quantity field is filled with a partial quantity in Production Check Task XYZ. After performing Finish Results Recording, the Inspected Quantity field and Finish Results Recording button become disabled, preventing further Inspection quantities from being entered.

(XYZ represents Production Check Task)

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Production Control Workcenter.
  2. Go to Task Control view.
  3. Search for Check Task ID XYZ.
  4. Choose Confirm.
  5. Under Inspection tab, Inspected Quantity is filled with a partial quantity.
  6. Choose Finish Results Recording.
  7. The Inspected Quantity field and Finish Results Recording button is disabled.

(XYZ represents Production Check Task)

Cause

  • Once Finish Results Recording is executed, the Inspection is considered completed and the fields under Inspection tab becomes read-only.
  • Therefore additional Inspection quantities cannot be recorded after executing Finish Results Recording.

Resolution

This is the standard system behavior.

Keywords

Finish Results Recording; Inspected quantity; Disabled; Check task; Inspection tab; Read-only; Partial quantity; Production Control; Task Control; Partial confirmation; Standard behavior , KBA , AP-PE-TSK , Production Task , Problem

Product

SAP Business ByDesign all versions