3798665 - How to enforce field "Budget Availability Control is Active" in Enterprise Projects

Symptom

Business requirement is to enforce the "Budget Availability Control is Active" checkbox as mandatory in Enterprise Projects.

Environment

  • SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Create an Enterprise Project in Project Control - Enteprise Projects.
  2. Requirement that "Budget Availability Control Active" fields is automatically checked.

Cause

Standard system behavior

Resolution

  1. No standard configuration exists to make field "Budget Availability Control is Active" mandatory.
  2. Implement extensibility BAdI /S4PPM/PROJECT_DETERMINATION to set "Budget Availability Control is Active" and assign the required "Budget Availability Control Profile" on project save.

See Also

App Extensibility: Project Control - Enterprise Projects

Keywords

enterprise project, budget availability control, availability control active, bac profile, non-editable after save, mandatory checkbox, edit budget control fields, project determination, /S4PPM/PROJECT_DETERMINATION, project management, eppm, public cloud, s/4hana cloud, budgeting, profile determination , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , How To