Symptom
When the Capacity Evaluation (transaction CM01) is accessed, the following behavior is observed after a partial or final confirmation is posted on a production/process order:
- The capacity requirement value is reduced
- The available capacity remains unchanged
- The capacity load % is reduced
- The remaining available capacity increases
It is questioned whether this is the correct system behavior, specifically whether confirmed capacity should or should not have an effect on the remaining available capacity.
Read more...
Environment
- SAP ERP Capacity Planning (PP-CRP)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA Cloud Private Edition
Product
Keywords
CM01, capacity requirements planning, remaining available capacity, available capacity unchanged, capacity load, partial confirmation, final confirmation, reduction of capacity requirements, outstanding requirements, work center, capacity evaluation, CRP, planning, SAP S/4HANA, CM01 behavior , KBA , PP-CRP-ALY , Capacity Evaluations , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.
SAP Knowledge Base Article - Preview