Symptom

  • Some curricula assigned to a user do not display the most recent completion timestamp for an item; instead, they show an older (second most recent) completion timestamp.
  • The issue occurs even when the item settings are identical across all affected curricula.
  • In the user interface, the Assigned Items tab can show a different completion date than expected based on the user’s overall learning history.

Environment

  • Product: SAP SuccessFactors Learning
  • Curricula

Reproducing the Issue

  1. Assign the same item to multiple curricula with identical item settings.
  2. Have the user complete the item (or receive credit via substitute/collateral credit).
  3. Review the item completion date within each assigned curriculum on the user’s Assigned Items tab.
  4. Observe that some curricula display an older completion date instead of the user’s latest overall completion for the item.

Cause

  • Expected behavior related to substitute/collateral credit: when a curriculum item is completed via collateral credit, the completion date stored for that curriculum reflects the latest substitute completion that existed at the time the item (or curriculum) was assigned. Future substitute completions are not continuously tracked to update completion dates of already assigned curricula.
  • If multiple substitute completions exist, the date captured depends on which completions existed up to the assignment date for that specific curriculum/item.

Resolution

This behaviour is working as designed.

Collateral credit acknowledges past learning at the time of assignment and does not continuously update existing curricula with newer substitute completions.

If the business need is for a curriculum to reflect a later completion date

You have two options:

  1. Complete the item directly — Have the user complete the current required item directly (without relying on substitute/collateral credit). This will align the completion date across all curricula containing the same item.

  2. Assign a new curriculum — Alternatively, assign a new curriculum containing the item. The new assignment will consider the latest available substitute completion at that time.

If this behaviour does not meet your requirements

Consider submitting an enhancement request through the standard SAP Influence channel to request ongoing updates of completion dates from future substitute completions.

See Also

Keywords

curriculum completion date, collateral credit, substitute item, assigned items tab, items completed, latest completion not shown, multiple curricula, item completion timestamp, curriculum assignment date, learning history mismatch, substitute credit behavior, retraining, curriculum item settings, event-based dates, ignore previous completions , KBA , LOD-SF-LMS-CUR , Curricula , Problem