Symptom
- In an on-premise environment, users can choose between creating a valuated or non-valuated project.
- In the public cloud environment, this selection option is not available during project creation.
- No error messages are displayed.
Environment
SAP S/4HANA Cloud Public Edition
Cause
- The selection of project stock valuation (valuated vs non-valuated) at project creation is not available in Public Cloud by design.
- Stock behavior is predefined by delivered project profiles and cannot be changed by users.
- The project stock indicator field (PROJ-KZBWS) from on-premise Project Builder (CJ01/CJ20N) is not exposed in the Project Control app.
- Non-valuated project stock is currently not supported in SAP S/4HANA Cloud Public Edition.
Resolution
- Acknowledge that selecting valuated vs non-valuated project stock during project creation is not available in Public Cloud by design.
- Use the delivered project profiles which define stock behavior:
- Investment Project: Valuated stock
- Overhead Project: No stock
- Statistical Project: No stock
- Project with Revenue: No stock
- Note that the project stock indicator field (PROJ-KZBWS) is not available in the Project Control app.
- Be aware that non-valuated project stock (quantity-only management without FI posting at goods receipt) is not supported in SAP S/4HANA Cloud Public Edition.
See Also
Keywords
valuated project, non-valuated project, project stock indicator, proj-kzbws, project control app, project builder, cj01, cj20n, s/4hana cloud public edition, public cloud, project profiles, investment project, overhead project, statistical project, project with revenue, missing option , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions
SAP Knowledge Base Article - Public