Symptom
The standard cost estimate of production/process order head material was released successfully.
However, when checking the order cost details, there is zero amount in Total Target Cost.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
Cause
The posting date of last GR is not during the Valid From and Valid To dates in the standard cost estimate.
For example, the posting date of last GR in the production order is 06/01/2026.
The Valid From and Valid To dates in the standard cost estimate(CK13N) are 06/30/2026 and 07/30/2026.
06/01/2026 is not during 06/30/2026 and 07/30/2026, the Total Target Cost will be displayed as zero.
Resolution
Make sure the posting date of last GR is during the Valid From and Valid To dates of the standard cost estimate.
Keywords
zero total Target cost, event-based order cost details, target costs missing, production order, process order, goods receipt, standard cost estimate missing, event-based costing, standard cost estimate, zero target amount, event-based production accounting , KBA , CO-PC-OBJ-ORD-2CL , Product Cost by Order (Public Cloud) , Problem
SAP Knowledge Base Article - Public