Symptom
- In the Delivery Schedule tab of a Stock Transfer Order (ME21N / ME23N), the GR End Date is significantly later than expected — gap between GI Date and GR End Date is much larger than the route transit time in days.
- No error message is raised; the discrepancy is a silent date calculation difference.
- Route configuration shows only transit duration (e.g., 70 days); no calendar is assigned to the route.
- MARC-WEBAZ (GR Processing Time) for the receiving plant is zero.
Read more...
Environment
- SAP S/4HANA
- SAP ERP Central Component
- SAP ERP
- SAP enhancement package for SAP ERP
Product
SAP ERP all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions
Keywords
GR date, GR end date, STO, stock transport order, scheduling, factory calendar, supplying plant calendar, working days, route calendar, transit time, delivery date, GI date, date calculation, MM-PUR, MM-PUR-GF-STO , KBA , MM-PUR-GF-STO , Stock Transfer , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results