Symptom
- Changing the WBS Element processing status from Created to Released in Project Control - Enterprise Projects is blocked.
- Error message FAA_CFG_CHECK 243 - 'CoCode &1, AssetCl &2: Ledger &3 not defined for AuC asset class'
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Create a new Investment Project using the Investment Project profile.
- Assign an Investment Profile to the project.
- Create a WBS element under the project.
- Open the WBS element in Project Planning.
- Change the Processing Status from Created to Released.
- Observe the error: "CoCode &1, AssetCl &2: Ledger &3 not defined for AuC asset class" and the release is blocked.
Cause
For the investment asset class, there is a limitation: The ledgers and depreciation areas defined in the company code MUST also be defined at the asset class level. Otherwise, you will encounter issues during settlement.
Resolution
Complete the configuration in SSCUI 102609 'Make Valuation View-Dependent Settings for Asset Class' accordingly.
Keywords
WBS release, Project Control, Enterprise Projects, AuC asset class, FAA_CFG_CHECK 243, 'CoCode &1, AssetCl &2: Ledger &3 not defined for AuC asset class', ledger 0L not defined, valuation view-dependent settings, SSCUI 102609, Asset Accounting, depreciation area, investment project, WBS status change, settlement configuration, S/4HANA Cloud Public Edition , KBA , FI-AA-AA-A-2CL , Master Data (Public Cloud) , Problem
SAP Knowledge Base Article - Public