Symptom
This document describes how the replenishment lead time is calculated for externally procured materials.
DISCLAIMER: Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Environment
SAP S/4HANA Cloud Public Edition
Resolution
The replenishment lead time represents the total time required to procure or manufacture an item. It is primarily used by the availability check to calculate the material availability date.
For externally procured materials, the replenishment lead time is calculated as follows:
Replenishment Lead Time = Purchasing Processing Time + Planned Delivery Time + GR Processing Time
- Purchasing Processing Time: can be found in configuration activity 102156 (Define Plant Parameters Overview), Planning Run section, default value of the External Procurement part.
- Planned Delivery Time: can be found in the Change Material app, MRP 2 view.
- GR Processing Time: can be found in the Change Material app, MRP 2 view.
Keywords
replenishment lead time, ATP, product availability check, externally procured material, planned delivery time, goods receipt processing time, purchasing processing time, confirmation date, material availability date, full confirmation, , KBA , CA-ATP-PAC-2CL , ATP: Product Availability Check (Public Cloud) , How To