3808976 - Calendar week column missing and translation issue in Manage Work Center Capacity app

Symptom

After 2608 release, the following issues happen in Manage Work Center Capacity app:

  • Chart label for hours/percentages appears in English instead of the selected language (e.g German).
  • The Operations table displays only 5 rows initially and relies on infinite scrolling to load more items.
  • The Shift Capacity table does not display a calendar week column.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Go to Manage Work Center Capacity app.
  2. Observe the hours label is still in English even if the language is German; the Operations table displays only 5 rows initially; calendar weeks are missing from the Shift Capacity table.

Cause

The "Only 5 tasks remain in the overview, with an infinite scroll bar" issue in Operations table is a part of the UX improvements in this release.

The translation and calendar weeks issues are known coding issue.

Resolution

Development team are working on the coding issue and the correction will be delivered with HFC06 on Nov. 18th.

Keywords

Manage Work Center Capacity, chart translation, English labels, operations table, scroll, calendar week, capacity planning , KBA , PP-CFS-SCH-2CL , Capacity Scheduling (Public Cloud) , Problem