3832349 - Cannot confirm yield quantity for secondary resources of process order

Symptom

When confirming secondary resources of a process order, there is no option to maintained the yield quantity.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Try to confirm secondary resources in confirmation app such as Confirm Process Order Phase (COR6N).
  2. Observe there is no place to enter the quantity data. 

Cause

This is standard system design.

For secondary resource, you can only confirm the following data:

  • Activities performed (for example, machine time, labor time, duration, or energy consumption)

  • Secondary Resource

Resolution

Maintain the activity values manually during the confirmation.

Keywords

process order, secondary resource, confirmation, yield quantity, activity, COR6N, Confirm Process Order Phase , KBA , PP-PI-POR-2CL , Process Order (Public Cloud) , Problem