Symptom
- The system does not allow adding a new note to a supplier confirmation line when creating a second supplier confirmation for the same purchase order item.
- The note from the previous supplier confirmation for the same item is automatically carried forward to subsequent confirmations.
- The option to add notes is grayed out when attempting to create a note again for the same item number.
- No error message or error code is displayed.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Create a supplier confirmation for a purchase order item and add a note at the confirmation line.
- Create a second supplier confirmation for the same purchase order item.
- Attempt to add a new note to the second supplier confirmation and observe that the add note option is disabled and the previous note is carried over.
Cause
- All supplier confirmations for the same purchase order (PO) item share a single text object at the PO item level. This is standard system behaviour — there is no mechanism to maintain separate, independent notes per individual supplier confirmation.
- As a result: When a second (or subsequent) confirmation is created, the existing note from the PO item level is carried over.
- The system is also unable to concatenate or merge texts from different supplier confirmations, since they all reference the same shared text object.
Resolution
This is the expected system behaviour. A direct fix is not available.
Workaround — Custom Text Field on Supplier Confirmation Item: To maintain an independent free-text note per individual supplier confirmation, a custom text field can be created at the Supplier Confirmation Item level:
- Navigate to Custom Fields and Logic in SAP S/4HANA Cloud Public Edition.
- Create a custom text field using the business context: MM_SUPLRCONF_ITEM.
- Each individual confirmation item can then have its own independent text maintained in this custom field.
- Note: The content of this custom field will not be transferred or synced to the PO item. It remains solely at the confirmation item level.
Keywords
supplier confirmation, add note grayed out, note carried forward, multiple confirmations, purchase order item, manage supplier confirmations, confirmation control, shipping notification, notes per confirmation, partial delivery, confirmed quantity, delivery date, supplier comments, MM-PUR-GF-CON, S/4HANA Cloud Public Edition , KBA , MM-PUR-GF-CON-2CL , Confirmation Control/Shipping Notification (Public Cloud) , Problem