Symptom
In a customer project, the project currency is different with the cost rate set in "Manage Cost Rates - Services" app and the revenue price set in "Manage Prices - Sales" app.
Hence, currency conversion is necessary under this situation.
You are wandering how the Planed Costs and Planned Revenues are calculated and which exchange rate type is used.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Go to "Plan Customer Projects" app
- Search for the project ID
- The Project Currency under 'Information' tab is for example USD
- Go to Work Packages tab and navigate into the specific work package
- You see the Planned Cost and Planned Revenue (for example SEK) for team roles and wandering how they are calculated
Resolution
For Planned Cost:
Currency conversion of planned cost in customer and internal projects is based on the exchange rate type specified in the baseline category (typically P) and the first day of the fiscal period.
However, if the project currency is equal to the global currency, an exception applies: amounts are always converted with the translation date 'first day of the fiscal year' and the rate type 'P'.
For Planned Revenue:
If the 'Advanced Revenue Strategy' is not activated in configuration activity "Settings for Professional Services Projects", the exchange rate is applied to each relevant period, respecting the first day of the fiscal period for rate type P.
See Also
- Refer to: Calculate Cost and Revenue
- Refer to: 2930207 - Currency Conversion in Activity Allocation and Plan Customer Projects
- Refer to: 3782821 - Planned cost in project currency converted again during cost calculation in "Plan Customer Projects" app
- Refer to: 3690041 - Plan Cost Calculation Logic for Customer Project Work Package
Keywords
planned cost, planned revenue, variance, currency conversion, exchange rate type P, fiscal year start, period start, pricing date, project currency, service organization currency, Plan Customer Projects, Professional Services, CA-CPD-SS, FX rate, revenue pricing, exchange rate, P, M , KBA , CO-OM-ACT-E-2CL , Postings (Public Cloud) , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem