Symptom
In a project-based production scenario with valuated project stock and availability control at WBS element level, the WBS budget check behaves differently depending on the Individual/Collective Indicator maintained in the material master (MRP 4 view):
-
When the Individual/Collective Indicator is set to 1 or left blank (Individual Requirements), no budget check is triggered, although a budget check is expected.
- When the Individual/Collective Indicator is set to 2 (Collective Requirements), the budget check is triggered, and message BP605 "Network activity budget exhausted" may be issued.
Read more...
Environment
- Controlling (CO)
- Project System (PS)
- SAP ERP
- SAP ERP Central Component
- SAP enhancement package for SAP ERP
- SAP enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA
- SAP S/4HANA Finance
- SAP S/4HANA Cloud Private Edition
Product
Keywords
CJ20N, BP605, availability control, WBS budget, individual/collective requirement, MRP 4, MARC-SBDKZ, project stock, production order, network activity, plan costs, budget exhausted, PS, PP integration, component assignment, CO01, CO02, CO03 , KBA , CO-PC-PCP , Product Cost Planning , PS-COS-BUD , Budget , PS-COS-PLN , Costs , Problem