Symptom
When using the "Convert Planned Orders to Production Orders" (CO41) or "Convert Planned Orders to Production Orders" (COHV) app to convert planned orders into production orders, the conversion process may fail after processing approximately 40 to 50 records (or a randomly varying number of orders), displaying the errors "HTTP 500 - Error: ICMETIMEOUT" and "A back-end error has caused the application to terminate."
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Go to app "Convert Planned Orders to Production Orders" - CO41.
- Enter plant and supervisor, then run the selection.
- Select multiple planned orders and start conversion to production orders.
- Observe that after roughly 40–50 conversions, the application terminates with HTTP 500 – ICMETIMEOUT and “A back-end error has caused the application to terminate.”
- The behavior can also occur when using app "Convert Planned Orders to Production Orders" - COHV for mass processing.
Cause
The behavior is expected for long-running SAP GUI transactions when converting large amounts of orders, which can lead to a timeout and termination.
Resolution
- Use the app F1718 “Schedule Order Conversion Runs” to process large volumes of planned orders in background jobs.
- Alternatively, use the Fiori app F4170 “Manage Planned Orders” and process in manageable batches.
- Refer to the documented behavior and guidance in the related note for timeouts of SAP GUI transactions launched from the launchpad.
See Also
Refer to: KBA 3507616 - T-code transaction on Fiori launchpad is terminated by timeout.
Keywords
HTTP 500, ICMETIMEOUT, CO41, COHV, convert planned orders, production orders, timeout, backend error, mass processing, Fiori launchpad, long-running transaction, schedule order conversion runs, F1718, F4170, manage planned orders , KBA , PP-SFC-EXE-2CL , Order Execution (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions
SAP Knowledge Base Article - Public