3838129 - WBS elements retain previous responsible cost center after copying project and assigning new responsible cost center to the project header

Symptom

After copying a project together with its WBS elements and assigning a new responsible cost center to the new project header, the copied WBS elements keep the previous responsible cost center from the source project instead of re-deriving from the new project-level assignment.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Copy an existing enterprise project along with its WBS elements.
  2. Assign the new project to a different responsible cost center so that a different company code is derived at the project header.
  3. Open the new project and verify the header shows the newly derived company code.
  4. Check the copied WBS elements and observe they still hold the previous responsible cost center from the source project.

Cause

Within enterprise projects, WBS elements can intentionally carry a different responsible cost center from the project header. During project copy, the WBS elements retain their source values, and updating the project header does not automatically cascade new responsible cost center assignments to the WBS elements.

Resolution

This is the expected system behavior.

To address the requirement of updating the responsible cost center across WBS elements in bulk, there are two workarounds:

Keywords

project copy, WBS elements, company code, responsible cost center, derivation, project header, project definition, enterprise project, re-derive, copy, BAdI, Project Element Determination, API_ENTERPRISE_PROJECT_SRV_0002, A_EnterpriseProjectElement, mass update, WBS , KBA , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , Problem