Symptom
- FC Req (Forecast Requirement) orders with zero quantity persist for a location product in SAP PP/DS after running /SAPAPO/MD74 (Report /SAPAPO/RM60RR20).
- No orders are selected when executing /SAPAPO/MD74 for materials with planning status 'Marked for Deactivation'.
- Transaction /SAPAPO/DELETE_FCREQ does not delete the forecasts because they were integrated from S/4HANA Core, not created locally in PP/DS.
- PP/DS deactivation cannot be completed due to remaining transactional data.
Read more...
Environment
• SAP S/4HANA Releases 2020 and onward.
• Production Planning and Detailed Scheduling (PP/DS)
Product
SAP S/4HANA 2020 ; SAP S/4HANA 2021 ; SAP S/4HANA 2022 ; SAP S/4HANA 2023 ; SAP S/4HANA 2025
Keywords
TsStkSb, FC Req, forecast deletion, PP/DS deactivation, /SAPAPO/MD74, /SAPAPO/RM60RR20, /SAPAPO/DELETE_FCREQ, planned independent requirements, zero quantity, location product, material planning status, Marked for Deactivation, pegging area, S/4HANA Core integration, PP/DS , KBA , SCM-APO-PPS , Production Planning and Detailed Scheduling , Problem