SAP Knowledge Base Article - Public

3839974 - Import to production blocked during maintenance uptime (Blue-Green deployment) — SAP S/4HANA Cloud Public Edition

Symptom

  • Transport to the production system is blocked.
  • The import option is currently unavailable.
  • Error: "System access currently restricted due to ongoing scheduled maintenance."
  • Error: "A system maintenance even is in process, please try again later"

Environment

  • Product: SAP S/4HANA Cloud Public Edition
  • Export Customizing Transports app

Reproducing the Issue

  1. Open the Export Customizing Transports app and attempt to import a software collection/transport into the production system.
  2. Observe that the import option is blocked or maintenance-related messages are shown during a scheduled maintenance/Blue-Green deployment uptime window.

Cause

  • The system is in Blue-Green deployment uptime preceding a scheduled maintenance window (CMP). During this period, functions that can impact cross-system consistency (for example, transport release/import and data migration) are intentionally blocked. Uptime typically starts about 12 hours before the maintenance period as per the 3SL maintenance schedule.

Resolution

  1. Verify whether the tenant is in a scheduled maintenance or Blue-Green uptime by checking official maintenance notifications and the 3SL maintenance schedule.
  2. Plan and perform transport imports outside the Blue-Green uptime and maintenance window. Wait until the maintenance has fully completed; the import option will become available automatically.
  3. If the import option remains blocked after maintenance completion, refresh the session/app and retry. If the issue persists, open a support case and provide timestamps and screenshots of the behavior.

1.

Hotfix Collection Application Changes after the 26... - SAP Community

 as per above u  are aware the CMP is  at   Saturday 15 UTC to 19 U

2.

 

S/4HANA Cloud Public Edition Systems Behaviour Dur... - SAP Community

 This community link has the  information  given below

"

For system updates, uptime starts about 12 hours before the maintenance period mentioned in the 3SL Maintenance Schedule.

What does Uptime allow or restrict?

Logically, the next question to follow is – which functionalities are allowed during Blue Green deployment uptime, and which are blocked?

To maintain consistency across the systems, it is important to put some restrictions around which functionalities are available during blue-green uptime. E.g. - certain system-specific functionalities and business transactions, including executing existing workflows, maintaining current settings, etc., are available during blue-green uptime, whereas other functionalities like release transports, data migration, etc., which can affect the consistency across systems, are blocked.

"

See Also

Keywords

transport import blocked, production import unavailable, import option disabled, scheduled maintenance, blue-green deployment, uptime window, CMP, 3SL maintenance, software collection import, customizing transport, transport management, S/4HANA Cloud, maintenance window, transport restrictions, deployment uptime , KBA , BC-CUS-TOL-CTO , Export Customizing Transports App , Problem