3840223 - “Maximum Production Receipt of 0.000000 Too Low” message in optimizer when no maximum production receipt is maintained

Symptom

After running the S&OP Optimizer with non-delivery explanation enabled, the explanation log (optimizer_expl) shows the following reason for unfulfilled customer demand:

"Maximum production receipt of 0.000000 too low. Raise at least by X.XXXXXX."

This message appears even though no Maximum Production Receipts are maintained for any product in the plan. The "current maximum production receipt" shown in the log is exactly 0.0.

Example:

Product: PXXXXX | Customer: CXXXXX | Location: LXXX | Period: CWXX 20XX
Requested: 0.00XXX | Fulfilled: 0.000000
Explanation row points to production source XXXXXX XXXX X (and component source CXXXXX XXXX X)
Both sources have a Production Freeze Horizon maintained on the Production Source Header (XX days and XX days respectively), but no Maximum Production Receipt master data is set

"Data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental."


Read more...

Environment

SAP Integrated Business Planning for Supply Chain (SCM-IBP)

Product

SAP Integrated Business Planning all versions

Keywords

Optimizer explanation, Maximum production receipt, Production freeze horizon, Bound resource, Non-delivery explanation, Unfulfilled demand, PFREEZEHORIZON, Production source header. , KBA , SCM-IBP-SUP-OPT , Supply Optimizer , Problem