Symptom
Duration value between PPX and legacy display different values.
Environment
Employee Central, Time Off
Reproducing the Issue
1. Open the employee's Job Information via People Profile > Job Data > Job Information.
2. On the Organization Information tab, select the Work Schedule link to open Work Schedule Details. Note Duration = 8 hr 15 min.
3. Open the legacy edit/history view for the same record and open the Work Schedule Details > Details tab. Note Duration = 07:15.
Expectation is that net duration is 7 hr 15 min (8 hr 15 min span minus the 60-minute break) should be showing in PPX as well.
Resolution
This is expected behaviour. Logic is that Duration should encompass everything and it's not exactly the working time of employee which means that the display in PPX is correct. Legacy behaviour is no longer valid and it is changed intentionally.
Keywords
Duration display ppx, legacy time , KBA , LOD-SF-EC-TIM-JOB , Time Management in Job Info - Records & Objects , Problem
SAP Knowledge Base Article - Public