3841537 - Indicator "Adjust Quantities in Order to Actual Values" in OPKP Is Set, But Operation Start Date Is Not Updated After Confirmation in CO11N

Symptom

The indicator "Adjust Quantities in Order to Actual Values" is activated in the production scheduling profile (T-Code OPKP). After posting a production order confirmation in T-Code CO11N, the operation start date is not updated and no rescheduling occurs. The expectation is that the operation start date reflects the actual confirmation date, but the date remains unchanged.


Read more...

Environment

  • SAP ERP Production Planning (PP)
  • SAP ERP All versions
  • SAP ERP Central Component All versions
  • SAP R/3 All versions
  • SAP R/3 Enterprise All versions
  • SAP S/4HANA All versions
  • SAP S/4HANA Cloud Private Edition All versions
  • SAP enhancement package for SAP ERP All versions
  • SAP enhancement package for SAP ERP, version for SAP HANA All versions

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

OPKP, Adjust Quantities in Order to Actual Values, operation start date, operation dates, rescheduling after confirmation, CO11N, production scheduling profile, OPKP scheduling, date adjustment, OPU3, PP-SFC-EXE-CON, confirmation scheduling, basic dates not updated , KBA , PP-SFC-EXE-CON , Confirmation , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.