Symptom
- A Work Center is defined with a Primary Capacity (e.g. Machine) and a Secondary Capacity (e.g. Pool, Labor, etc.)
- In the Routing an Operation was maintained to be performed in this Work Center and durations were specified for multiple parameters (Setup, Machine, Labor)
- A PDS was integrated and planned orders were created in PP/DS side
- Symptom:
- Upon opening the DS Planning Board, it shows the Activity duration is the same in both resources (primary and secondary)
- Upon checking the Capacity Requirements in the Resource Utilization chart, in Monitor Capacity Utilization app or in transaction /SAPAPO/CDPS_REPT, it shows the same value for both resources
Read more...
Environment
- SAP S/4HANA
- SAP Supply Chain Management (SCM)
- Production Planning and Detailed Scheduling (PP/DS)
Product
SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions
Keywords
KBA , SCM-APO-INT-MD-PDS , Production Data Structure , SCM-APO-PPS-SCF , Scheduling Functions , SCM-APO-PPS , Production Planning and Detailed Scheduling , SCM-APO-PPS-CP , Capacity Planning , SCM-APO-PPS-EVA , Evaluation , Problem