SAP Knowledge Base Article - Public

3843122 - Planned costs ignored for expense type with multiple G/L accounts causing incorrect POC in Event-Based Revenue Recognition (SAP S/4HANA Cloud Public Edition)

Symptom

  • Actual posting to a G/L account assigned to an expense type is not considered POC relevant in Event-Based Revenue Recognition, resulting in an unexpected percentage of completion (POC).
  • In the revenue recognition simulation, only the first G/L account assigned to the expense type appears in the planned dataset; other G/L accounts under the same expense type are treated as Non-POC relevant until the first G/L is recognized by the cost source.
  • No error messages are displayed.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Configure an expense type with multiple G/L accounts in Define Expenses.
  2. Ensure the cost source used by Event-Based Revenue Recognition (for example, a cost element group for planned COS) does not include the first (lowest-numbered) G/L account assigned to that expense type.
  3. Post an actual cost to a different G/L account under the same expense type (not the first one).
  4. Run the Event-Based Revenue Recognition simulation/log review for the project.
  5. Observe that the actual posting is treated as Non-POC relevant and the POC is calculated unexpectedly.
  6. Include the first G/L account in the EBRR cost source (or post on the first G/L), rerun the simulation, and observe that postings under the expense type become POC relevant.

Cause

Only the first (lowest-numbered) G/L account assigned to an expense type is used by Event-Based Revenue Recognition as the plan basis; because the EBRR cost source did not include that first G/L account, actuals posted to other G/L accounts under the same expense type were not considered POC relevant.

Resolution

  1. Include the first (lowest-numbered) G/L account assigned to each relevant expense type in the EBRR cost source (for example, the cost element group YBPS_E00* used for Expense E00*).
  2. If you need a different G/L account to serve as the reference for plan transfer, adjust G/L assignments so that the intended account is the first one under the expense type. As accounts are sorted ascending by number, you cannot manually reorder; move other G/L accounts to a different expense type if necessary.
  3. Rerun Event-Based Revenue Recognition simulation and verify that actual postings to any G/L account under the expense type are considered POC relevant and that the POC is calculated as expected.

See Also

Keywords

POC incorrect, planned cost of sales missing, expense type multiple G/L, first G/L account, cost element group, plan transfer ACDOCP, EBRR, revenue recognition simulation, Non-POC relevant, Define Expenses, plan basis, CPM project plan transfer, planned COS, percentage of completion, plan data selection , KBA , CO-PC-OBJ-EBR-2CL , Event-Based Revenue Recognition (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions