Symptom
- The start date of a task displayed as sometime this year (for example, October 18, 2026, at 16:30), but the start date shown when clicking the exclamation icon is sometime in a future year (for example, November 1, 2028, at 00:13).
- Error message: “Set the end date to be later than the start date.”
- Unable to set the end date back to the current year (for example,2026) due to the discrepancy in dates.
Environment
SAP ANALYTICS CLOUD 1.0
Reproducing the Issue
1. Open the SAC Calendar.
2. Observe the task start date displayed as sometime this year (for example, October 18, 2026, at 16:30).
3. Click the exclamation icon beside the start date to see the start date as sometime in a future year (for example, November 1, 2028, at 00:13).
4. Attempt to update the task's end date to a date within the current year (2026).
5. Encounter the error: “Set the end date to be later than the start date.”
Cause
- Check the filed "Start By" of the task process and find it is set to be "dependency", which means it has parent tasks.
- The end date of the parent process is manually overridden to the time in the future year (for example, November 1, 2028, at 00:13).
- When the end date of the parent process is changed in SAC Calendar, child tasks and sub-processes have their planned dates recalculated proportionally to fit within the new parent window. Even though all the child tasks already ran and completed in October 2026, their planned dates — which SAC uses for dependency calculations — were all pushed forward into 2028 along with the parent.
This is why every task in the chain shows !: the actual execution happened in 2026, but the system-calculated planned dates are in 2028.
Resolution
Fixing individual child tasks directly will not work and will keep returning the error, because the dependency calculation originates from the parent.
The correct sequence is top-down:
Step 1 — Edit the parent process and change its End Date.
• Open Details panel
• Edit the End Date from Nov 1, 2028 back to an appropriate 2026 date (e.g., the original intended end date)
• Save — this will trigger recalculation of all child planned dates
If you get the error "“Something went wrong while updating the event. Please refresh the application in your Web browser and try again.” , please refer to the KB 3843698
Step 2 — Update the end date of the child task.
See Also
Knowledge Article KBA 3731193 - Calendar process tasks automatically delayed at start date without errors - SAP Analytics Cloud
Keywords
KBA , LOD-ANA-PL-PRO , Planning Process, Input Task, Calendar Task , Problem
SAP Knowledge Base Article - Public