Symptom

When planning with alternative resources, the finite heuristic in IBP may create capacity conflicts. This occurs because the heuristic uses a greedy algorithm that makes locally optimal resource assignments without considering downstream demand that may have no alternative resource available.

A planner observes that:

  • A production order for Product B is scheduled on Resource 1 with a capacity conflict (overload).
  • Resource 2 is available and unused.
  • Product A was planned earlier on Resource 1, even though Resource 2 was also a valid alternative for Product A.

The planner expects IBP to have assigned Product A to Resource 2 in order to keep Resource 1 free for Product B.


Read more...

Keywords

KBA , SCM-IBP-RM-FH , Order-Based Finite Heuristic , How To

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.