Symptom
When planning with alternative resources, the finite heuristic in IBP may create capacity conflicts. This occurs because the heuristic uses a greedy algorithm that makes locally optimal resource assignments without considering downstream demand that may have no alternative resource available.
A planner observes that:
- A production order for Product B is scheduled on Resource 1 with a capacity conflict (overload).
- Resource 2 is available and unused.
- Product A was planned earlier on Resource 1, even though Resource 2 was also a valid alternative for Product A.
The planner expects IBP to have assigned Product A to Resource 2 in order to keep Resource 1 free for Product B.