SAP Knowledge Base Article - Preview

3846613 - MRP Live not generating supply elements at supplying plant in intracompany scenario with PP/DS

Symptom

• In an intracompany scenario, MRP Live does not generate supply elements at the supplying plant.
• The receiving plant material is not Advanced Planning-relevant (MRP type PD), while the supplying plant material is PP/DS-relevant (MRP type X0).
• Alternatively, the receiving plant material is PP/DS-relevant with PP/DS scope limitation 3 (display only), and the supplying plant material is fully PP/DS-relevant.
• No stock transfer requisitions are created in PP/DS at the source location.


Read more...

Environment

  • SAP S/4HANA
  • SAP Supply Chain Management

Product

SAP S/4HANA all versions ; SAP Supply Chain Management all versions

Keywords

MRP Live, supplying plant, stock transfer, MRP type X0, scope limitation, Advanced Planning, T-lane, multi-level MRP, synchronous integration, stock transport requisition, MD04  , KBA , SCM-APO-PPS , Production Planning and Detailed Scheduling , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.