Symptom
- A delivery date is changed and saved in ECC (Outbound or Inbound Delivery).
- In SAP TM, the associated Freight Unit (FU) is updated: the requirement time window fields (Required Start / Accepted Start / TRQ Required Start) reflect the new delivery date.
- The Freight Order (FO) that was created by the VSR Optimizer remains on its original planned dates and is not updated.
- The Freight Order shows an execution block with block category "Time Conflict" (BLOCK_CAT = Q, constant sc_block_category-time_conflict defined in /SCMTMS/IF_COMMON_C). The block is set by user TM_REMOTE.
- The same delivery date change on a Freight Order created by manual planning does not produce this block.
Read more...
Environment
- SAP Transportation Management embedded in SAP S/4HANA 1709 and higher.
Product
SAP S/4HANA all versions
Keywords
BLOCK_CAT Q, time conflict, execution block, PLAN_TRANS_TIME, TRQ_REQ_START, REQ_START, ACC_START, optimizer freight order, VSR optimizer, delivery date change, ECC delivery date, freight order dates not updated, UPDATE_FROM_RELATED_TORS, time_conflict block, block category time conflict, rescheduling, LogInt, logistics integration, S/4HANA TM, TM_REMOTE, BLK_EXEC, DATES_SETBY PD , KBA , TM-PLN-VSR-OPT , Optimizer , Problem